ROACH DRY LAKE, Nev. — Not a light bulb’s worth of solar electricity has been produced on the millions of acres of public desert set aside for it. Not one project to build glimmering solar farms has even broken ground.
Instead, five years after federal land managers opened up stretches of the Southwest to developers, vast tracts still sit idle.
An Associated Press examination of U.S. Bureau of Land Management records and interviews with agency officials shows that the BLM operated a first-come, first-served leasing system that quickly overwhelmed its small staff and enabled companies, regardless of solar industry experience, to squat on land without any real plans to develop it.